Environmental Impacts by A. D. Moonasingha
IWEM: CONFERENCE 1991
A Paper Presented at the Annual
Conference of the IWEM at Birmingham in April 1991
THE ENVIRONMENTAL IMPACTS OF
MAHAWELI RIVER ENGINEERING AND RESERVOIR CONSTRUCTION PROJECT
By
A.D.MOONASINGHA. B.Sc (Hons),
M.Eng. (Graduate)
INTRODUCTION
The Mahaweli Ganga (River) rises above an altitude
of 1200m on the Hatton plateau of the westerly central hills of Sri Lanka,
flows in northern and easterly directions winding its way around Kandy the
historic hill capital, following few rapids to the east, flows through the low
lying coastal plains of the eastern dry zone, and enters the Indian Ocean at
Trincomalee on the north eastern coast (Fig 1). The Mahaweli Ganga, the longest
in Sri Lanka, is 206 miles long and discharges an annual flow of some 7900 million
cubic meters [1].
The construction of the Mahaweli
Project initially
commenced in 1970 with the interbasin transfer diversion headworks at Polgolla
near Kandy [1,2]. The Polgolla complex comprising a barrage, tunnel and a
hydropower station at Ukuwela, was completed in 1976. This early programme of
construction under the phase 1, stage 1 also included a hydropower station at
Bowatenna in the Amban Ganga basin – a tributary of Mahaweli River which is was
commissioned in 1981. This complex also transfers water for irrigation in the
North central Province.
The original master plan of the Mahaweli Project
was for completion in 30 years, but in 1977, driven by the political exigency
to meet the growing socio-economic and power supply needs of the country, led
to the accelerated implementation of the remaining major phase of the project,
with bilateral and multilateral aid. This constituted the construction of four
major reservoirs and three hydropower stations which saw the completion and
commissioning during the period 1981 – 1990. The accelerated programme also
encompasses most of major irrigation settlement systems in which the settlement
is Lanka nearing completion [4]. The Mahaweli Development Project irrigates
some 100,000 ha of land in the dry zone, including enhancement of irrigation
supplies to over 53,420 ha of existing irrigation lands: and has the capacity
to generate 2 million megawatt hours of hydroelectric energy per year. The
(Figs 2 and 2a) illustrate the Mahaweli interbasin transfer water distribution
network system.
Fig 1. Mahaweli River Dam
Projects, Sri Lanka
ACCELERATED MAHAWELI PROGRAMME
This major phase of the Mahaweli Project comprised
the construction of major Dams and headworks,
namely Kotmale, Victoria, Randenigala, and Rantambe,
illustrated in (Fig 1) [5]. Kotmale Project the most upstream of the Mahaweli
cascade is located on the Kotmale Oya, a tributary of Mahaweli Ganga (Fig 3).
The Kotmale Project has posed both serious geological and financial problems of
construction, and consists of a rockfill dam incorporating a reinforced
concrete face [1,5,6]. The Victoria Project is located on the
Mahaweli Ganga approximately fourteen miles downstream of the Polgolla
Barrage, and consists of a double curvature concrete arch dam. Below Victoria
is the Mahaweli’s biggest reservoir, Randenigala comprising a
rockfill dam with clay core. Downstream of Randenigala is the medium
sized Rantambe Project, the last of the reservoirs on the Mahaweli
cascade which was completed in 1990 [3]. The Maduru Oya Project is
another major reservoir in the Mahaweli Accelerated Programme, located on the
Maduru Oya basin in the Eastern Province adjacent to the lower Mahaweli
catchment [1,4]. The completion of irrigation settlement Systems B,C and G of
the downstream developments are operations of the Accelerated Programme [1].
Fig 2a. Topographic Map of Sri
Lanka
Fig 2. Mahaweli Water
Distribution Network
Fig 3. Kotmale Hydropower
Project Layout
DAM GEOLOGY
The geology of Mahaweli Ganga dam sites primarily
consists of metamorphic rocks of PreCambrian age [7,8]. However, Mahaweli dam
sites are also associated with Karst geological features.
The site investigations have revealed that rock strata underlying Kotmale dam
comprise cavernous limestone beds with widened joints dipping downstream, and
weak charnockites with an orientation of foliation shear. These
geological weaknesses led to the shifting of Kotmale dam to a position 200m
downstream from the original location which contributed to the increased cost
and subsequent reduction of dam height with reduced capacity from its potential
[5,7]. Limestone caverns were also encountered during the construction of the
foundations of the Victoria arch dam project.
Sri Lanka is considered to be an area of low
seismicity [8,9]. Cases of too rapid filling behind dams 90m or more
high inducing seismicity have been cited [5]. On account of the above
and the large size of the dams of Kotmale, Victoria and Randenigala, and the
presence of well developed major lineaments in and around these projects, a
micro-seismic network was installed in 1982 to measure any increase in seismic
activity during and after impounding of the reservoirs. No such increase in
seismicity along the lineaments has been observed [8]. During the period of
monitoring, clusters of seismic events of less than Richter scale 2 have been
recorded in the major reservoir region in the hills of the Mahaweli upper
catchment, and in the System B and C areas beside Maduru Oya region in the
Eastern Province [9].
Fig 8. Maduru Oya Rock-fill Dam - Environment
DOWNSTREAM SETTLEMENTS
The downstream human settlements in the
dry zone under the Mahaweli irrigation schemes are demarcated into zones which
are called Systems [1,4]. These Systems occupy large areas of the Eastern, and
North Central provinces as shown in the (Fig 9).
Over 256,000ha, almost two thirds of the total
proposed land area of Mahaweli Project lands, were covered with forest. Chena
(slash and burn) cultivation extended over 39,660ha or 10 percent of the total
land area under the project. About 6,070ha of privately owned paddy lands and
highlands in the ‘System H’ were acquired under the Mahaweli Project for
resettlement [1].
The System H lying in the Kalawewa catchment in the
North Central Province has a total area of 30,769ha, and is augmented or fed by
the waters transferred at Polgolla Barrage. The irrigation infrastructure
developments in the System H area included improvements to the Kalawewa and
Kandalama reservoirs, construction of new reservoirs, the improvement of
existing village reservoirs, and construction of a thousand and one
distributary canals [1].
The System C in the Eastern Province, being an
underdeveloped area with 23,886ha in extent, required more miles of roads,
besides about 1,000 miles of irrigation canals, roads and a vast array of
social infrastructure buildings common to all Systems. The conditions in System
B with 47,773ha under Maduru Oya Project are similar to that of System C.
Apart from the increased rice production,
alternative subsidiary crop production during Yala (South West
monsoon, May – July) season is a successful programme in the Mahaweli
Development Project [1,4].
Fig 9. Map of Mahaweli Project
Irrigation Settlements
IRRIGATION
Before the coming of the Mahaweli inter-basin
transfer augmentation, most irrigation schemes had the characteristic of
isolation. Since the first century AD there has been augmentation of few major
reservoirs from the diversion works (anicuts - weirs) of Amban Ganga (tributary
of Mahaweli River) and the Mahaweli Ganga1. The majority of diversions feeding
the reservoirs in the dry zone have received their yield from the North East
monsoon or Maha season from December to February, with an average annual rainfall
about 1650mm. In most schemes this North East monsoon yield is inadequate for
the irrigation of two successful cultivation seasons a year. The unique
advantage of Mahaweli Ganga diversion inter-basin transfer is that the Mahaweli
upper catchment receives its run-off from the rainfall in both monsoons in the
island, and in most months of the year, with an annual rainfall of 4,000mm to
5,000mm [1,10]. The increased reliability of irrigation water for both
cultivation seasons Maha (December – February, April) and Yala (May –
September) of the year attributed to Mahaweli Development has made a
significant benevolent impact compared with isolated local irrigation schemes
that do not benefit from the Mahaweli waters.
The seepage losses are an important factor in
irrigation schemes [1,16,19]. Therefore few major canals constructed across
well drained soils in the Eastern Province, such as Maduru Oya main and branch
canals are concrete lined [1].
Few cases of salinity have been reported in
the System H irrigation area. From soil and irrigation water tests
carried out, one report has deduced that water is of tolerable quality for
irrigation with provision for leaching [21]. Another survey promulgates
significant increase of total salt concentration, sodium (SAR) and residual
carbonates (RSC) in irrigation waters in the Kalawewa area of the System
H, in April (end of Maha season harvesting period), and to a certain extent in
November (end of late Yala season harvesting period) [22]. Some well waters
sampled in the System C area in the Eastern Province have been found unsuitable
for irrigation, because of high salinity indicators [12].
PUBLIC HEALTH
Malaria has been an endemic tropical disease
in Sri Lanka from time immemorial. Nevertheless, with modern preventative and
curative campaigns, malaria was virtually eradicated from the island in the
early sixties. Stagnated pools of water are favourable sites for breeding the
malaria vector Anopheles mosquito [23]. However, since the late seventies when
the Mahaweli settlements commenced, malaria has been an endemic disease in the
North Central Province, and is regarded as a threat to community health in many
regions of Sri Lanka [13,23,24,25]. Vigorous preventative – prophylactic, and
curative campaigns have been relaunched since the beginning of settlement in
the Mahaweli Project areas [26]. Schistosomiasis (bilharzia) a most commonly
associated disease with large irrigation projects in the tropics, is not found
in Sri Lanka [13,27]. Water-borne gastroenteritis and other
diarrhoeal infections are common in the Mahaweli Project areas, but not acute
[26,28]. There has been an outbreak of cholera in 1974 in the Mahaweli
settlement area that lasted until 1976 [13]. Mortality of infants and children
from diarrhoea is almost absent [28]. Japanese encephalitis (dengue) is
reported a major health problem in Sri Lanka; though the main vector breeds in
rice fields, outbreaks have been reported in parts of the country peripheral to
the Mahaweli settlement areas [23]. All in all the health situation in the
Mahaweli Development areas is not markedly different from the rest of the
country, except for instance the danger of malaria.
The main source of drinking water supply is shallow
wells fitted with hand-pumps. A small percentage of households have their own
wells. Except the wells near reservoirs many dry out during the dry season.
Also after few years wells fall into decay with covers removed and hand-pumps
broken and removed. The deep wells (borehole tube wells) produce a small yield
and rarely dry out, and can serve about 50 families; the capital cost is high,
about 5 times the cost of a shallow well, but more economic and beneficial.
Drinking water supply from shallow wells in the region is inadequate and the
settlers travel long distances in the dry season to wells with water, main
canals, and reservoirs to fetch water [13,28]. To improve the conditions deep
wells are being constructed in favourable locations [28]. Standpipe water
supplies are available in many townships in the Mahaweli Development [29]. The
construction and use of lavatories are very poor. Less than 40 percent of
households have lavatories. Out of latrines built, about 35 percent are water
sealed type and the others are pit latrines [28].
SOCIAL IMPACTS
The important social impacts can be identified in
the two aspects of displacement from the reservoir construction areas, and
resettlement in the new irrigation systems. The acquisition of private lands in
the settlement areas also has had a similar impact.
A large number of families were evacuated from the
Victoria and Kotmale reservoir sites. A majority of these people were resettled
in the downstream settlements and the others have opted to resettle in the
provisions made in the Kandy District, and Kotmale respectively [2,8]. Also the
private lands and chena (slash and burn) cultivations coming under the new
development areas were acquired and their owners were resettled [1]. As the
Victoria reservoir inundated old shanty-towns, new towns were built to replace
what were lost8. Fisheries are inspired in all large reservoirs. The
availability of fish and the demand have encouraged people to take up fishing
as a new livelihood [8,29].
New settlers in the downstream developments begin
with both physiological and psychological stress. Except the small proportion
of settlers who come from the dry zone, others come from a milder climate than
the harsh dry climate in the downstream settlements. Physical tiredness, and
sickness associated with the change in climate and poor drinking water supplies
can easily hinder the progress of settlers’ initial work. Inter alia, the fear
of wild animals, danger of snakes, and personal conflicts among the new
arrivals causing a general feeling of insecurity are psychological components
of the settlers [8].
A well formulated socio-economic welfare system is
provided for the benefit of the women and children. The Mahaweli irrigation
settlement Systems are managed by a team including vocational advisors of
several disciplines.
Training programmes for the training of junior
managers, and for community participation have been successful and popular
[28]. Farmers in Sri Lanka are in general adapted to semi-mechanical and
scientific cultivation practices. The overall mechanisation of rice cultivation
is still in its infancy, but developing.
A remarkable impact outside the Mahaweli
development area itself is the extensive rural electrification with the benefit
of Mahaweli hydropower projects.
ENVIRONMENT
The Mahaweli
Project areas
can be considered in two separate regions as the upper catchment, and the
downstream developments.
The extent of upper catchment which comprises the
major reservoir catchments is more than 316,000 hectares [11]. In this area the
intensively managed land comprised about 49 percent of which two thirds was
mainly tea; 14 percent was covered in forest. The rest of the land consisted of
dry land agriculture, chena cultivation, abandoned tea and grassland. The main
annual temperature in the region varies little from 27 oC [10].
The previous practice of tobacco and chena
cultivation has been banned from the immediate reservoir catchments as a means
of reducing soil erosion, and they are encouraged to cultivate more permanent
crops. Where tobacco is grown, cultivators are encouraged to implement soil
conservation techniques. All estates in the catchment are required to provide
sufficient ground cover in all ravines and gullies [29]. The Kotmale valley has
a record of mass movements. There is no conclusive scientific evidence to show
that Kotmale reservoir and its operations have caused the cracks and serious
damage to houses in the area [27].
It is cited that soil erosion can be as high as 308
– 913 tonnes/ha/annum in badly managed tobacco lands [8]. Neglected tea
plantations are also a source of heavy soil erosion [27]. On the other hand a
well maintained tea cover provides best protection to soil [8]. With an
estimated average annual sediment yield of 300 m3/sq kilometre, with allowance
for bed load, the total sediment load is about 1mm3 per year. It is considered
that this sedimentation rate would not impair the effective operating capacity
of the reservoirs for more than 50 years [10].
The Water Resources Board has found that
groundwater is heavily polluted by agrochemicals in some of the tube wells
drilled in the area around Nuwara Eliya, making it unsuitable for human
consumption [8]. The heavy use of fertiliser and agrochemicals in the tea
estates and the vegetable plots poses a serious problem to the Mahaweli
reservoirs. The fact that Mahaweli waters are conveyed a considerable distance
through the inter-basin transfers, highlights the need for vigilance on
monitoring water quality in the Mahaweli areas [8].
Flood peaks in the Mahaweli Ganga will be
considerably reduced by the storage in the new reservoirs and controls in the
headworks. The Kotmale dam is built below its maximum capacity due to cost
escalation attributed to geological weaknesses discovered during the
construction. Victoria reservoir is built for maximum capacity without
flooding Polgolla. The new hydrology of Mahaweli Ganga particularly below the
dam sites could increase stagnant pools favourable for breeding malaria
spreading mosquitoes [23,24,27].
Swollen river conditions of Amban Ganga attributed
to overloading by Mahaweli diversion operations have been sighted. The
replenishment and spilling of many reservoirs in the dry zone augmented by the
Mahaweli waters are now influenced more by the diversion operations than the
mass curve hydrograph based on local catchment inflows. In the downstream areas
the clearance of forest will increase the runoff factor; the paddy fields with
water retaining bunds will control the runoff, and increase the base flow. In
the same context the evapotranspiration will be reduced, but the evaporation
will increase from the imported waters covering large surface areas. The
reduction of downstream flows of Mahaweli Ganga may influence the saline
intrusion to the lower flood plain. This can be aggravated by return flows of
irrigation [10].
All reservoirs will show some thermal and chemical
stratification with reduced oxygen at bottom layers; except the very deep major
reservoirs will probably mix one or more times a year [10,12]. In the Kotmale
reservoir the establishment of aquatic and semiaquatic vegetation is slow [27].
The reservoirs on Mahaweli Ganga will adversely affect the river fish marshier
and several other species. Many other species such as tilapia and carp with
demand as a food fish will proliferate [10,29]. The diminution of the species
marshier is not considered a loss, because it occurs in large numbers in other
rivers [10]. The flood plain Villus (riverine wetlands) are a landscape feature
liable to be affected adversely. Reduction in seasonal inflow of water may
cause successive change of the semiaquatic ecosystem favourable for the
survival of several wildlife species, particularly wading birds [10,11].
Under the reforestation programme, as a means of
protecting the upper catchment of Mahaweli, several thousand acres have already
been reforested [29]. Fuelwood plantations in the downstream development
Systems are implemented. In Systems B and C all the available supplies will be
exhausted before the plantations are ready for use, and this will result in
degradation of the fuelwood development [29].
As the downstream settlement projects are
implemented, the mammals are displaced and move into remaining forest habitats
in the surrounding areas. Displaced animals entering these habitats
causes overcrowding. Imbalances in the natural ecosystems may result in a
decrease in wildlife populations. Damage to paddy and other crops by
displaced elephants have increased since the accelerated downstream
development [3,10]. Water holes in the Wilpattu National Park have been
improved to increase the carrying capacity [2,9]. About seven
protected wildlife reserves have been declared covering a land area
of over 230,000 hectares. These reserves have varying degrees of protection,
from strict nature reserves to wildlife corridors. Encroachment of forest land
in the settlement System and the Flood Plain National Park, is a persistent
problem [29].
There is potential for tourism development in
Victoria, Randenigala, and Maduru Oya reservoirs with wildlife attractions at
Maduru Oya. Archaeological remains in the project areas are benefitted by the
development; action has been taken to preserve and exhibit them. New roads have
been constructed to re-route the stretches of inundated roads, and a new road
link on the left bank of the mahaweli River facilitated by the Victoria Dam.
There are signs of neglect of old highway infrastructure in the upper catchment
that could be attributed to continuing civil unrest in the country. Modern road
links have been constructed to remote settlement regions.
Fig
13. Pinnawela Elephant Orphanage
OPERATIONS
A key issue in the water use of Mahaweli Project is
the amount of water diverted at Polgolla Barrage and the amount routed along
the Mahaweli Ganga to Victoria and Randenigala. Victoria is treated favourably
with regard to the availability of Mahaweli water, because it has better
economic returns of water use20. Mahaweli Project has more than doubled the
power generation capacity of the country with an increased capacity of 600MW.
The augmentation facility has changed the mean water level of the large reservoirs
augmented by Mahaweli, attributed to the operational easement provisions
available. Illustration (Fig 2) depicts the Mahaweli operations network.
CONCLUSIONS
As a result of political impetus, the major
headworks and other infrastructure of the Mahaweli Development Project were
implemented during the period 1981 – 1990 under an accelerated programme, with
bilateral and multilateral aid.
Engineering geology of the upper catchment of
Mahaweli is problematic and its adverse effects have aggravated the
construction of the Kotmale Dam. Microseismic activity has been monitored with
clusters of magnitude less than 2 Richter scale recorded adjacent to Victoria
reservoir, and in the Maduru Oya region distributed on Systems B and C. An
increase of microseismic activity due to impoundment of large dams has not
occurred.
The river ecosystem in the upper catchment has been
replaced with a deep reservoir ecosystem. A programme of soil conservation,
planned vegetation, and reforestation to protect the Mahaweli upper catchment
is being implemented.
In the Mahaweli distribution system, more water is
routed through Victoria along Mahaweli cascade, which is deemed as the
favourable economic operational policy. Contemporaneous with downstream flood
prevention, the flood plain Villus could be affected by hydrosere succession.
Mahaweli Project provides irrigation with increased
reliability to a large area of existing and new lands in the dry zone. The
Mahaweli Project lands exhibit sustained green environment in contrast to
irrigation schemes in the dry zone which are not fed by Mahaweli waters. Some
effects of salinity have been reported in the Kalawewa basin under the System H
area. All in all the health conditions in the Mahaweli settlements are not much
different to the rest of the country.
The agricultural developments of the Mahaweli
Project have cleared a vast area of forest land in the dry zone and destroyed
wildlife habitats. Repercussive damage to cultivations by elephants has
increased. The downstream forest environment has been replaced with an
irrigated agricultural environment beneficial to humans, rich in aquatic
resources and lush vegetation. New wildlife parks have been established. The
Mahaweli Project has not caused an extinction of species of fauna and flora,
but caused environmental disturbances which contribute to a reduction in
endangered species populations.
ACKNOWLEDGEMENTS
The author is grateful to the Minister of Lands,
Irrigation and Mahaweli Development, Mr P Dayaratne, and the Mahaweli Authority
of Sri Lanka, for their kind permission to research for this paper. Grateful
acknowledgements are also due to other institutions and officials for assisting
with the field visits and enquiries. The author gratefully appreciates the
publications and other works listed in the references, on which this paper is
based.
REFERENCES
1. Karunatilake, H.N.S. The Accelerated Mahaweli
Programme and its Impact. Centre for Demographic and Socio-economic Studies,
Sri Lanka. 1988.
2. Vistas of Mahweli. Newsletter of the Mahaweli
Centre of the Mahaweli Authority of Sri Lanka. Vol.5, No. 3, 6. March 1990
3. Ibid, Vol. 5, No. 2, February 1990.
4. Acclerated Mahaweli Programme. A summary report,
Mahaweli Authority of Sri Lanka. Undated.
5. Brown, K. Kotmale – the dam that moves.
Construction News magazine. Vol. 8, No, 8, p 18-25, 1982.
6. Gosschalk, E.M. and Dr.Kulasinghe, A.N.S.
Kotmale Dam and Observations on CFRD. Proceedings of a Symposium sponsored by
the ASCE, Concrete Face Rockfill Dams. Detroit p 379-395, 1985.
7. Sir William Halcrow and Partners. Kotmale
Hydropower Project. Technical brochure.
8. Vitanage, Bulankulama, Adikaram, and Madduma
Bandara, Victoria Dam and its Impact. A seminar held at Hotel Hantana, Kandy,
Sri Lanka. 1986.
9. Final Report on Kotmale Microseismic Studies,
Sri Lanka. Department of Earthquake Engineering, University of Roorkee, U.P.
India 1984.
10. USAID. Environmental Assessment, Mahaweli
Development Programme, Ministry of Mahaaweli Development, Colombo, Vol. 1.
1980.
11. Ibid. Terrestrial Environment. Vol. II.
12. Ibid. Aquatic Environment, Vol. III.
13. Ibid. Human Environment. Vol. IV.
14. Acres International Ltd. Organisational
Aspects, Mahaweli Water Resources Management Project, Water Management
Secretariat, Colombo, Canadian International Development Agency, Canada. 1984.
15. Ibid. Studies of Operating Policy Options, Main
Report, 1985.
16. Ibid. Policy Studies Briefing Document,
Appendix I.
17. Ibid. Irrigation Water Requirements, Appendix
II.
18. Ibid. Basic Data, Appendix III.
19. Ibid. Acres Reservoir Simulation Programme,
Appendix IV.
20. Ibid. Economic Aspects of Water Use, Appendix
V.
21. Handawela, H., A study on inland salinity in
Mahaweli System H area, Mahaweli Authority of Sri Lanka, undated.
22. Gunawardhana, H.D., Kumudini, A.M., and
Adikari, R., Studies on the quality of irrigation waters in Kalawewa area,
University of Colombo, J. Natn. Sci. Coun Sri Lanka, 9(2) p 121-148, 1981
23. Joint WHO/FAO/UNEP, panel of experts on
environmental management for vector control. Proceedings of the workshop on
irrigation and vector-borne disease transmission, International Irrigation
Management Institute, Sri Lanka. 1986.
24. Dr. Wijesundara, M. Daily News, Sri Lanka,
Friday, April 6 1990. p 15
25. Patrick, W.K. Primary health care in the
Mahaweli, UNICEF sponsored health education bureau publication. 1983
26. Dr. Nichalson, A, et al, Aid in Confidence,
Report on an Overseas Development Ministry Health Mission to Sri Lanka. 1978.
27. Johanson, D. Kotmale Environment, Swedish
International Development Authority Evaluation Report, SIDA, Stockholm.
28. National Institute of Business Studies
Management, Evaluation of the Project, Social development benefitting children
and women in System H of Mahaweli development area, Colombo. 1989.
29. Dr. Sobczak, M.T., Mahaweli Environmental
Update, USAID, Colombo.
Appendix
System H of
Mahaweli Development Project, USAID.
http://pdf.usaid.gov/pdf_docs/PNAAT993.pdf
Mahaweli
Projects & Programme 1983 Schematic map of Mahaweli irrigation settlements
http://pdf.usaid.gov/pdf_docs/PDAAX272.pdf
Mahaweli
water management to maximise benefits
http://publications.iwmi.org/pdf/H023566.pdf
The
Mahaweli Strategy of Sri Lanka — Great Expectation of a Small Nation. C. M.
Madduma Bandara
http://link.springer.com/chapter/10.1007%2F978-94-009-5458-8_27
Comments
Post a Comment